A Comprehensive Solution for Stranded Fuel Oil
The Problem
A power generating facility had 77,000 barrels of fuel oil that were no longer needed, but the owner had several challenging issues:
CThe Altiras Solution
Altiras managed the process by:
- Conducting a thorough assessment of the product, storage tanks, site, P&ID’s, piping, valves, equipment, and all the detailed requirements, including many issues not covered by the RFQ.
- Developing a comprehensive plan that included all the physical changes to the site for piping and connections, engineering drawings, all equipment, written processes and procedures, and brought in all the appropriate personnel to ensure the safe removal of the product and loading of the railcars.
- Coordinated and leased a rail spur, registered the site with both the Pipeline and Hazardous Materials Safety Administration (PHMSA) and the Department of Transportation (DOT) to ensure full compliance, and managed 35 railcars, turning each one four times.
Results
Altiras demonstrated exceptional project management and execution by completing the removal of the stranded fuel oil within the designated time frame, without incident. The customer was so impressed with the work they asked Altiras to remove the fuel oil from the underground pipelines running to and from the power plant. Altiras completed this additional task within the original project time frame. Altiras’ success on this project is a strong indication of the company’s capability and reputation for delivering high-quality, timely, and effective services.